Latest
2026.09
The unloading of MPs (monopiles) has commenced. Major wind turbine components have arrived at Akita Port for the first time.
Preparations for upcoming offshore construction are underway at the port.
2026.05
The erection of a 2,500-ton crawler crane has been completed.
Preparations are underway for the upcoming assembly of wind turbine components.
2026.05
The Akita Port Office has been completed and is now in operation.
It is being utilized as a local base to support offshore construction work.
2025.08
Site preparation at the base port has been completed. Ground improvement work will now begin in earnest.
The necessary workspace has been prepared for receiving and assembling wind turbine components.
Latest
2026.07
As part of the switching station construction, equipment assembly is underway on the completed foundations.
2026.06
As part of the substation construction, foundation work is underway for the installation of equipment.
2026.05
As part of the onshore transmission line construction, pipe jacking work is underway in preparation for pulling the submarine cables onshore.
2026.03
As part of the substation construction, foundation work is underway for the installation of equipment.