Construction Progress

Construction Schedule

Scroll horizontally to view

Offshore Construction (including Akita Port)

  • 2026.05

    The erection of a 2,500-ton crawler crane has been completed.
    Preparations are underway for the upcoming assembly of wind turbine components.

  • 2026.05

    The Akita Port Office has been completed and is now in operation.
    It is being utilized as a local base to support offshore construction work.

  • 2025.08

    Site preparation at the base port has been completed. Ground improvement work will now begin in earnest.
    The necessary workspace has been prepared for receiving and assembling wind turbine components.

Onshore Facilities Construction

  • 2026.06

    As part of the substation construction, foundation work is underway for the installation of equipment.

  • 2026.05

    As part of the onshore transmission line construction, pipe jacking work is underway in preparation for pulling the submarine cables onshore.

  • 2026.03

    As part of the substation construction, foundation work is underway for the installation of equipment.

Column—Daily Progress—

There are no posts to display at this time.