Onshore Facilities Construction Construction Progress

  • 2026.07

    As part of the switching station construction, equipment assembly is underway on the completed foundations.

  • 2026.06

    As part of the substation construction, foundation work is underway for the installation of equipment.

  • 2026.05

    As part of the onshore transmission line construction, pipe jacking work is underway in preparation for pulling the submarine cables onshore.

  • 2026.03

    As part of the substation construction, foundation work is underway for the installation of equipment.

  • 2026.02

    As part of the onshore transmission line and substation construction, power cables are being laid through underground manholes and cable conduits.

  • 2025.08

    Substation construction has commenced. Equipment installation is underway to connect the wind farm to the transmission grid.

  • 2025.06

    Onshore transmission line and substation construction has commenced. Conduit burial work is currently underway, followed by manhole construction and cable laying.